You don't need to finish the whole bathroom in one day — work one wall at a time, corner to corner.

You do not have to apply the Tadelakt Finish to your whole bathroom in one day. In fact, you should only apply the Tadelakt Finish coats to one wall at a time.

How to Sequence a Multi-Wall Tadelakt Project

  1. Apply the Tadelakt finish coats inside corner to inside corner, on one wall (plane) at a time.

  2. Finish that wall completely, including the application of the Olive Oil Soap Sealer.

  3. Allow the finished wall to cure at least 12 hours before applying the adjacent wall.

Why it matters: Working corner to corner on a single plane lets you complete each wall as one continuous, fully sealed surface, with clean transitions at the corners.